Bitcoin miner · Landlord (leases built data halls)

TeraWulf (WULF) AI data centers

TeraWulf leases data halls to AI tenants with Google standing behind much of the rent. It has 839 MW of contracted critical IT: 438 MW at Lake Mariner, New York (Fluidstack and Core42) and 401 MW at Justified in Kentucky (Anthropic, 20 years, about $19 billion). 102 MW was operating on September 30, 2026.

Figures checked on November 18, 2026 against Form 10-Q and investor update, Q3 2026 (November 6, 2026). Every number links to the document it came from.

Key figures

TeraWulf AI data center figures with sources
FigureWhat the company reportsSource
Contracted capacity839 MWQ3 2026 investor updateas of September 30, 2026
Operating (billing) capacity102 MWQ3 2026 earnings releaseas of September 30, 2026
PipelineAbout 2.1 GWQ3 2026 investor updateas of November 6, 2026
Contract valueAbout $27BQ3 2026 investor updateas of November 6, 2026
Debt$5.8B total debtQ3 2026 investor updateas of September 30, 2026
CashAbout $2.4B incl. restrictedQ3 2026 earnings releaseas of September 30, 2026

A figure the company has not disclosed shows as n/a. Capacity is critical IT load unless marked as gross power, so compare like with like on the leaderboard.

Tenants and partners

  • Fluidstack Named in a filing

    378 MW at Lake Mariner, 10-year leases, backed by about $3.2 billion of Google credit support at WULF Compute

    Q3 2026 investor update
  • Core42 Named in a filing

    60 MW at Lake Mariner, 10-year lease

    Q3 2026 investor update
  • Anthropic Named in a filing

    About 401 MW at Justified, Hawesville KY, 20 years plus two 5-year options, about $19 billion; Google credit backstop for the project financing

    Form 8-K, Nov 4, 2026

Landlord or GPU owner?

Does not own the GPUs. TeraWulf builds and leases the data halls; its WULF Compute unit builds within guidance of $8 million to $10 million per critical IT MW.

How the four models differ in risk and return is explained in landlord, powered land or GPU cloud.

What TeraWulf said on its latest call

Q3 2026 earnings release, investor update and call, November 6, 2026. From Earnings release and investor update filed with Form 8-K.

  • HPC lease revenue was $63.0 million, about 83% of third-quarter revenue of $76.2 million.
  • At Lake Mariner, CB-4 (168 MW) is being handed over in phases in November and December 2026, and CB-5 (168 MW) is targeted for the first quarter of 2027.
  • Justified's three buildings (125.6, 137.6 and 137.6 MW) are due from the fourth quarter of 2027 to the second quarter of 2028, with Fluor as EPC contractor.
  • CEO Paul Prager said "Muskie gives us a contracted path to a gigawatt of power"; the company reaffirmed a target of 250 to 500 MW of new contracted critical IT a year.

Lake Mariner and Justified

TeraWulf's first campus, Lake Mariner in Barker, New York, has 438 MW of critical IT under contract. 102 MW across five buildings was earning lease revenue on September 30, 2026, and two more buildings of 168 MW each are under construction. The tenants are Fluidstack (378 MW) and Core42 (60 MW) on 10-year leases. The slides put contracted revenue at about $8 billion and expected average annual net operating income at about $700 million once the site is fully running.

The second campus, Justified in Hawesville, Kentucky, is leased whole to Anthropic: about 401 MW for 20 years with two 5-year options, worth about $19 billion over the initial term. The Kentucky regulator has approved 482 MW of electric service. Rent starts as each data hall is delivered, from late 2027.

Pipeline beyond the contracted 839 MW

The slides list about 2.1 GW of future development: Muskie in Grayson, Kentucky (about 800 MW of IT on power contracts now expanded to 1 GW, pending state approval), Lake Hawkeye in Lansing, New York (about 320 MW) and Chesapeake Data & Energy in Maryland (about 800 MW, an acquisition not yet closed). None of these has a tenant yet; management says it is in active talks for Muskie.

Debt and funding

Total debt was $5.8 billion on September 30, 2026: $2.5 billion of convertible notes at the parent, $3.2 billion of senior secured notes at WULF Compute and $75 million drawn on the revolver. Cash, equivalents and restricted cash totalled about $2.4 billion. TeraWulf sold its 50.1% stake in the Abernathy joint venture for about $530 million, with $250 million received in the quarter and the rest due by April 2027.

Recent news

  • 2026-11-04Announced Google credit support for the project financing behind the Anthropic lease, and a definitive EPC agreement with Fluor for three buildings at Justified. (Form 8-K, Nov 4, 2026)
  • 2026-10-23Amended its revolving credit agreement, raising commitments from $250 million to $400 million. (Form 8-K, Oct 23, 2026)

What to watch next

  • CB-4 rent starting on schedule in November and December 2026, and CB-5 in early 2027.
  • Kentucky approval of the 1 GW Muskie power agreements and a first Muskie tenant.
  • Whether annual signings land inside the 250 to 500 MW target.

TeraWulf AI data center FAQ

Who are TeraWulf's AI tenants?

Fluidstack (378 MW) and Core42 (60 MW) at Lake Mariner, and Anthropic (about 401 MW) at Justified. Google provides credit support behind the Fluidstack leases and the Justified financing.

How much AI capacity is TeraWulf running?

102 MW of critical IT was operating on September 30, 2026, out of 839 MW contracted; 737 MW was under construction.

Does TeraWulf buy GPUs?

No. It is a landlord: it develops and leases the data halls, and the tenants bring the computers.

Other companies on the tracker

Back to the AI data center tracker. This page is information, not investment advice.

Important: Educational Purposes OnlyThe data, charts, treasury tracking metrics (including mNAV and SPS), and research provided on CryptosEyes.com are for informational and educational purposes only. They do not constitute certified financial, investment, or trading advice. Digital assets like Bitcoin and Ethereum are highly volatile. Always conduct your own research and consult with a registered financial advisor before making investment decisions.