- Home
- AI Data Center Tracker
- CleanSpark
Bitcoin miner · Landlord (leases built data halls)
CleanSpark (CLSK) AI data centers
CleanSpark has signed its first AI lease: a 175 MW critical IT campus at Sandersville, Georgia, leased to Meta for 20 years, about $6.6 billion of base-term value, with first delivery in the fourth quarter of 2027. It funded the build with $2.276 billion of 7.875% secured notes. It still mines bitcoin across about 1.8 GW of contracted power.
Figures checked on November 18, 2026 against Investor presentation and notes offering (Sep 2026); 10-K for the year to Sep 30, 2026 due late November (September 25, 2026). Every number links to the document it came from.
On this page
Key figures
| Figure | What the company reports | Source |
|---|---|---|
| Contracted capacity | 175 MW | Investor presentation, Sep 2026as of September 17, 2026 |
| Operating (billing) capacity | None yet (Q4 2027) | Investor presentation, Sep 2026as of September 17, 2026 |
| Pipeline | About 1.8 GW contracted power (mostly mining today)Gross power, not critical IT load | Investor presentation, Sep 2026as of September 17, 2026 |
| Contract value | About $6.6B | Investor presentation, Sep 2026as of September 17, 2026 |
| Debt | $1.78B (Jun 30) before $2.276B of new notes | Form 10-Q (Jun 30, 2026) and Form 8-K (Sep 25, 2026)as of June 30, 2026 |
| Cash | $203M | Form 10-Q, quarter to Jun 30, 2026as of June 30, 2026 |
A figure the company has not disclosed shows as n/a. Capacity is critical IT load unless marked as gross power, so compare like with like on the leaderboard.
Tenants and partners
Meta Named in a filing
Sandersville, GA: 175 MW critical IT, 20 years plus two 5-year options, triple-net, rent from November 30, 2027
Investor presentation filed Sep 17, 2026
Landlord or GPU owner?
Does not own the GPUs. Sandersville is a triple-net lease; Meta supplies its own computers.
How the four models differ in risk and return is explained in landlord, powered land or GPU cloud.
What CleanSpark said on its latest call
Investor presentation for the Sandersville notes, September 17, 2026. From Presentation filed with Form 8-K.
- Sandersville "provides 175 MW of long-duration critical IT capacity to support Meta's growing AI, data-processing and communications requirements".
- Development cost is about $11.9 million per IT MW; projected average annual NOI is about $330 million at about 100% NOI margin under a triple-net lease.
- Rent begins November 30, 2027 after the first network hand-over; the presentation targets initial delivery in the fourth quarter of 2027.
- CleanSpark provides a completion guarantee if the note proceeds fall short.
Sandersville and Meta
CleanSpark's September 2026 presentation names Meta as the tenant at Sandersville, Georgia: 175 MW of critical IT under a 20-year base term with two 5-year extension options and one 12-month option. The lease is triple-net, so Meta pays operating costs and CleanSpark expects close to a 100% NOI margin, about $330 million a year on average. Base-term contract value is about $6.6 billion.
This is CleanSpark's first AI lease and it is not yet built. Rent begins on November 30, 2027, after the first hand-over, and the company targets initial delivery in the fourth quarter of 2027.
Debt and the rest of the business
A CleanSpark subsidiary sold $2.276 billion of 7.875% senior secured notes due 2031 in September 2026 to fund the rest of Sandersville, secured on that project, with a parent completion guarantee. Before that, debt was about $1.78 billion on June 30, 2026. CleanSpark controls about 1.8 GW of contracted power across the United States, most of it still used for bitcoin mining. Its fiscal-year 10-K, for the year to September 30, 2026, is due in late November and will update these figures.
Recent news
- 2026-09-25Closed $2.276 billion of 7.875% senior secured notes due 2031, issued at 98.5% of par, to finish Sandersville. (Form 8-K, Sep 25, 2026)
What to watch next
- The 10-K for the year to September 30, 2026, due late November, and any second AI lease.
- Construction progress toward the fourth-quarter 2027 hand-over.
- Which of the other sites in its 1.8 GW portfolio it offers for AI.
CleanSpark AI data center FAQ
Who is CleanSpark's AI tenant?
Meta, named in CleanSpark's September 2026 presentation, for 175 MW of critical IT at Sandersville, Georgia over 20 years.
When does CleanSpark start earning AI rent?
Rent begins November 30, 2027, with initial delivery targeted for the fourth quarter of 2027.
How did CleanSpark fund Sandersville?
With $2.276 billion of 7.875% senior secured notes due 2031 issued by a project subsidiary in September 2026.
Other companies on the tracker
- Core Scientific (CORZ)
- IREN
- Cipher Digital (CIFR)
- TeraWulf (WULF)
- Galaxy Digital (GLXY)
- Hut 8 (HUT)
- Riot Platforms (RIOT)
- Applied Digital (APLD)
- MARA Holdings (MARA)
- Bitdeer (BTDR)
- HIVE Digital Technologies (HIVE)
- Keel Infrastructure (formerly Bitfarms) (KEEL)
- Nebius Group (NBIS)
- CoreWeave (CRWV)
Back to the AI data center tracker. This page is information, not investment advice.