Bitcoin miner · GPU cloud (owns the GPUs, sells compute)
IREN AI data centers
IREN buys its own GPUs and sells AI cloud compute, while also owning the land, power and buildings. AI cloud revenue was $200 million in the quarter to September 30, 2026, revenue backlog was $20.3 billion, and it says more than $4 billion of annual run-rate revenue is contracted and funded for January 2027. Microsoft is its best-known customer.
Figures checked on November 18, 2026 against Form 10-Q and Q1 FY27 results (quarter to Sep 30, 2026) (November 5, 2026). Every number links to the document it came from.
On this page
Key figures
| Figure | What the company reports | Source |
|---|---|---|
| Contracted capacity | About 300 MW (IT) behind the $4B+ contracted run rate | Q1 FY27 resultsas of September 30, 2026 |
| Operating (billing) capacity | About 93 MW AI cloud operating | Form 10-Q, quarter to Sep 30, 2026as of September 30, 2026 |
| Pipeline | >5 GW secured power; >35 GW early-stage pipeline (company calls it speculative)Gross power, not critical IT load | Q1 FY27 resultsas of November 5, 2026 |
| Contract value | $20.3B backlog | Q1 FY27 resultsas of September 30, 2026 |
| Debt | $10.04B principal | Form 10-Q, Note 19as of September 30, 2026 |
| Cash | $3.52B (+$2.26B restricted) | Form 10-Qas of September 30, 2026 |
A figure the company has not disclosed shows as n/a. Capacity is critical IT load unless marked as gross power, so compare like with like on the leaderboard.
Tenants and partners
Microsoft Named in a filing
Horizon 1 at Childress went into service for Microsoft with NVIDIA GB300 NVL72 systems; Horizons 2 to 4 in late-stage construction
Q1 FY27 resultsNVIDIA and 13 other customers Named in a filing
Two-thirds of the $20.3 billion backlog is with investment-grade counterparties
Q1 FY27 resultsA "Leading Frontier AI Lab" Not named
Existing contract expanded after quarter end; the lab is not named
Q1 FY27 results
Landlord or GPU owner?
Owns the GPUs and runs the cloud. Some customers prepay: a five-year contract signed after quarter end has the customer prepaying 90% of the GPU cost.
How the four models differ in risk and return is explained in landlord, powered land or GPU cloud.
What IREN said on its latest call
Q1 FY27 results and webcast, November 5, 2026. From Results release filed with Form 8-K.
- Co-CEO Daniel Roberts said the $4 billion-plus contracted run rate is now targeted for January 2027 after "a customer-requested design change and supplier timing", and may extend to the end of February.
- After quarter end IREN signed a five-year contract at about $22 million of revenue per MW with 90% of GPU capex prepaid, and a short-term contract at $40 million per MW.
- Pricing on new contracts rose 11% for 3-year deals and 12% for 5-year deals; H100s were recontracted at double the earlier price.
- Remaining planned FY27 capex is $15 billion: $9 billion is covered by cash, committed GPU financing and prepayments, and $6 billion still has to be raised.
Why IREN is a GPU cloud, not a landlord
Most miners in this tracker rent out empty, powered halls. IREN fills its own halls with GPUs it buys and rents out computing time. That is why its revenue per MW is far higher (its new five-year deal is about $22 million per MW a year) and also why its capital needs are far larger: it pays for chips that lose value over a few years, not only for buildings that last 20.
In the quarter to September 30, 2026 AI cloud revenue was $200 million: $135 million from cloud services and $65 million booked as lease revenue. Bitcoin mining fell to $28 million as installed hashrate shrank to about 7.9 EH/s from 45.3 EH/s a year earlier. IREN sold every coin it mined and held no bitcoin on its balance sheet.
Contracts, power and the January target
IREN does not report contracted capacity in MW the way landlords do. It reports backlog ($20.3 billion, up 22% in the quarter) and annual run-rate revenue (ARR). It says a 0.3 GW (IT) program supports the $4 billion-plus ARR target, which slipped from the end of 2026 to January 2027 and could run to the end of February. Operating AI cloud capacity was about 93 MW on September 30.
On power it claims more than 5 GW secured on over 30,000 acres, and a pipeline above 35 GW that the release itself calls speculative, with most not expected to become secured power. The tracker shows the secured figure for comparison and keeps the 35 GW as a note.
Debt and funding
Debt principal was $10.04 billion on September 30, 2026, including $6.75 billion of convertible notes due 2029 to 2033. Cash was $3.52 billion plus $2.26 billion of restricted cash, so net debt, as IREN calculates it, was $4.43 billion, up from $216 million a quarter earlier. The company has about $6 billion of FY27 funding still to find, from GPU financing, prepayments, data center financing or other sources.
Recent news
- 2026-11-05Sweetwater Hub (2 GW) received conditional inclusion in ERCOT's Batch Zero process as base load; a 300 MW civil works licence was secured in Badajoz, Spain. (Q1 FY27 results)
What to watch next
- Whether the $4 billion-plus run rate is live by January 31, 2027, or slips to February.
- How the remaining $6 billion of FY27 capex is funded, and how much dilution the convertible notes bring.
- Which customer the expanded "Leading Frontier AI Lab" contract is with, if IREN names it.
IREN AI data center FAQ
Does IREN buy its own GPUs?
Yes. IREN owns the GPUs as well as the land, power and data centers, and sells AI cloud compute. Some customers prepay part of the GPU cost.
Who are IREN's AI cloud customers?
The filed results name Microsoft and NVIDIA and say there are 13 other customers. A "Leading Frontier AI Lab" expanded its contract after quarter end but is not named.
What is IREN's revenue backlog?
$20.3 billion on September 30, 2026, about two-thirds of it with investment-grade counterparties.
Other companies on the tracker
- Core Scientific (CORZ)
- Cipher Digital (CIFR)
- TeraWulf (WULF)
- Galaxy Digital (GLXY)
- Hut 8 (HUT)
- Riot Platforms (RIOT)
- Applied Digital (APLD)
- CleanSpark (CLSK)
- MARA Holdings (MARA)
- Bitdeer (BTDR)
- HIVE Digital Technologies (HIVE)
- Keel Infrastructure (formerly Bitfarms) (KEEL)
- Nebius Group (NBIS)
- CoreWeave (CRWV)
Back to the AI data center tracker. This page is information, not investment advice.