Bitcoin miner · Powered land (tenant brings the compute)

Riot Platforms (RIOT) AI data centers

Riot Platforms has leased 1,151 MW of critical IT, worth about $38 billion, mostly to one unnamed "Frontier AI Lab". Its biggest deal, all 910 MW of the Corsicana campus, is a powered land lease: Riot supplies land, power and pads, and the tenant brings and runs modular compute. AMD also leases capacity at Rockdale.

Figures checked on November 18, 2026 against Form 10-Q and Q3 2026 results (November 4, 2026). Every number links to the document it came from.

Key figures

Riot Platforms AI data center figures with sources
FigureWhat the company reportsSource
Contracted capacity1,151 MWQ3 2026 resultsas of November 4, 2026
Operating (billing) capacityNot stated (AMD halls live; $18.4M data center revenue in Q3)Q3 2026 resultsas of November 4, 2026
Pipelinen/a (whole Corsicana campus now leased)Q3 2026 resultsas of November 4, 2026
Contract valueAbout $38BQ3 2026 resultsas of November 4, 2026
Debt$657M, plus a $573M equipment facilityForm 10-Q, Q3 2026as of September 30, 2026
Cash$950.2M cash and bitcoinQ3 2026 resultsas of September 30, 2026

A figure the company has not disclosed shows as n/a. Capacity is critical IT load unless marked as gross power, so compare like with like on the leaderboard.

Tenants and partners

  • A "leading Frontier AI Lab" (not named) Not named

    Corsicana: all 910 MW, 15-year triple-net powered land lease, about $28 billion; Rockdale: 191 MW, 20 years, delivered December 2027 and June 2028

    Q3 2026 results and Form 10-Q
  • AMD Named in a filing

    50 MW at Rockdale with an option up to 200 MW; AMD exercised part of the option, with 10 MW due in November 2026

    Form 10-Q, Q3 2026

Landlord or GPU owner?

Does not own GPUs. At Corsicana the tenant will "procure, install, own, and operate" its modular compute and pay power as a pass-through.

How the four models differ in risk and return is explained in landlord, powered land or GPU cloud.

What Riot Platforms said on its latest call

Q3 2026 results and call, November 4, 2026. From Results release filed with Form 8-K.

  • CEO Jason Les called the Corsicana deal "the largest lease in Riot's history" and said the contracts should produce more than $2 billion of average annual NOI at full deployment.
  • Total capital cost at Corsicana is about $6 million per IT MW, "about half the capital of a Tier 3 build", because the tenant supplies the compute buildings.
  • Riot does "not currently anticipate issuing equity" for announced projects; it sold 20,264 bitcoin this year for about $1.5 billion, mainly to fund development.
  • Rent at Corsicana is payable on the full 910 MW irrespective of utilization.

A powered land landlord

Riot's Corsicana lease is a different model from the turnkey halls most peers build. Riot delivers the land, the high- and medium-voltage power infrastructure and the powered pads, and keeps owning and maintaining that infrastructure. The tenant procures, installs, owns and operates modular compute on the pads and pays substantially all operating costs, including power. That cuts Riot's cost to about $6 million per IT MW and limits its building risk, at the price of a lower rent per MW than a full data hall would earn.

The lease covers the whole 332-acre Corsicana parcel, 910 MW of critical IT, for 15 years. Riot puts it at about $28 billion of contract value and about $1.8 billion of average annual rent over the initial term.

Rockdale: AMD and the same AI lab

At Rockdale, AMD leases 50 MW with an option to grow to 200 MW, and exercised part of that option in 2026, with 10 MW due in November 2026. The same Frontier AI Lab signed a 20-year lease for 191 MW at Rockdale earlier in 2026, delivered in phases in December 2027 and June 2028. Data center revenue was $18.4 million in the third quarter, out of $181.4 million total.

Debt and funding

Riot has funded the shift mostly by selling bitcoin rather than borrowing. Long-term debt was $657 million on September 30, 2026, and in September it repaid and closed a Coinbase credit facility of up to $200 million. A Morgan Stanley-led facility of up to $573 million funds Rockdale equipment. Cash and bitcoin totalled $950.2 million at quarter end, and no equity was raised in 2026.

Recent news

  • 2026-08-10Signed a Morgan Stanley-led delayed-draw term loan of up to $573 million for long-lead equipment for the 191 MW Rockdale project. (Form 8-K, Aug 14, 2026)

What to watch next

  • Whether Riot names the Frontier AI Lab, or the lab announces it.
  • Delivery of the Rockdale 191 MW in December 2027 and June 2028.
  • How long bitcoin sales can fund construction before Riot needs new debt.

Riot Platforms AI data center FAQ

Who is Riot's AI tenant?

Riot describes it only as a leading frontier AI lab and has not named it. The lab leases all 910 MW at Corsicana and 191 MW at Rockdale; AMD separately leases capacity at Rockdale.

What is a powered land lease?

Riot supplies land, power infrastructure and powered pads; the tenant brings, owns and runs its own modular compute and pays the power bill. Riot spends about $6 million per IT MW.

How much has Riot contracted for AI?

1,151 MW of critical IT worth about $38 billion, as of its November 4, 2026 results.

Other companies on the tracker

Back to the AI data center tracker. This page is information, not investment advice.

Important: Educational Purposes OnlyThe data, charts, treasury tracking metrics (including mNAV and SPS), and research provided on CryptosEyes.com are for informational and educational purposes only. They do not constitute certified financial, investment, or trading advice. Digital assets like Bitcoin and Ethereum are highly volatile. Always conduct your own research and consult with a registered financial advisor before making investment decisions.