Bitcoin miner · Landlord (leases built data halls)

Hut 8 (HUT) AI data centers

Hut 8 is building two AI data center campuses with turnkey leases: River Bend in Louisiana (245 MW of critical IT) and Beacon Point in Texas (two 352 MW leases with one tenant). It puts total base-term contract value at about $26.6 billion. The first data hall is due in the second quarter of 2027, so nothing is operating yet.

Figures checked on November 18, 2026 against Form 10-Q and Q3 2026 results (November 4, 2026). Every number links to the document it came from.

Key figures

Hut 8 AI data center figures with sources
FigureWhat the company reportsSource
Contracted capacity949 MW (245 + 352 + 352)Form 10-Q and Q3 2026 resultsas of November 4, 2026
Operating (billing) capacityNone yet (first hall Q2 2027)Q3 2026 resultsas of November 4, 2026
Pipeline3,180 MW under exclusivityGross power, not critical IT loadQ3 2026 resultsas of November 4, 2026
Contract valueAbout $26.6BQ3 2026 resultsas of November 4, 2026
Debt$7.5B non-recourse project financingPress release filed Sep 28, 2026as of September 28, 2026
Cash$157MForm 10-Q, Q3 2026as of September 30, 2026

A figure the company has not disclosed shows as n/a. Capacity is critical IT load unless marked as gross power, so compare like with like on the leaderboard.

Tenants and partners

  • Fluidstack (Anthropic partnership) Named in press reports

    River Bend, 245 MW of critical IT on 330 MW of utility capacity; reported as part of a multi-gigawatt partnership with Anthropic

    DatacenterDynamics report
  • Not named (investment-grade tenant) Not named

    Beacon Point, two 352 MW leases on 1,000 MW of utility capacity; Phase 2 alone is about $9.8 billion of base-term value

    Q3 2026 results

Landlord or GPU owner?

Does not own GPUs for these campuses; the leases are triple-net and take-or-pay. Hut 8 is exiting its small Traditional Cloud business.

How the four models differ in risk and return is explained in landlord, powered land or GPU cloud.

What Hut 8 said on its latest call

Q3 2026 results and call, November 4, 2026. From Results release filed with Form 8-K.

  • CEO Asher Genoot said both projects are expected "to be funded entirely at the project level, without requiring equity issuance or recourse debt at the parent".
  • The Beacon Point tenant signed a second 352 MW lease, "doubling its contracted capacity at the campus"; expected average annual NOI across Beacon Point is about $1.3 billion.
  • Energy capacity under exclusivity rose by 1,300 MW to 3,180 MW, and Hut 8 agreed to buy two energized West Texas sites (up to 230 MW) for up to $180 million.
  • Hut 8 bought back $74.7 million of shares in the quarter and $175.3 million more after it, paid for by selling bitcoin.

Two campuses, all leased before they are built

River Bend in St. Francisville, Louisiana is a turnkey data center with 245 MW of critical IT on 330 MW of utility power. Structural steel and foundations are complete across all four data halls and the substation is partly energized; the first hall is due in the second quarter of 2027. The tenant is reported to be Fluidstack, as part of its partnership with Anthropic; the filings do not name it.

Beacon Point in Texas has 1,000 MW of utility capacity under construction for two 352 MW leases with the same, unnamed, investment-grade tenant. Phase 1 is due in the third quarter of 2027 and Phase 2 in the second quarter of 2028. Hut 8 puts the Phase 2 lease at about $9.8 billion of base-term value and about $655 million of average annual NOI, and the campus as a whole at about $19.6 billion and $1.3 billion.

How it is funded

Hut 8 has raised $7.5 billion of fully amortizing, non-recourse, investment-grade project financing for the two campuses, including $3.25 billion of notes for River Bend. In September it added a $1.07 billion revolving credit facility at the parent. Cash was only $157 million on September 30, 2026, but Hut 8 held 16,787 bitcoin (3,090 of them pledged to Bitmain), which it has been selling to fund buybacks.

Recent news

What to watch next

  • The first River Bend data hall in the second quarter of 2027, the company's first AI revenue at scale.
  • Whether Hut 8 or its tenant names the Beacon Point customer.
  • Closing of the two West Texas sites and how much of the 3,180 MW under exclusivity becomes contracted.

Hut 8 AI data center FAQ

Who leases Hut 8's data centers?

River Bend is reported to be leased to Fluidstack as part of its Anthropic partnership. Beacon Point's tenant is described only as investment-grade and has not been named.

When does Hut 8 start earning AI data center rent?

The first data hall is targeted for the second quarter of 2027 at River Bend, then Beacon Point Phase 1 in the third quarter of 2027 and Phase 2 in the second quarter of 2028.

How is Hut 8 paying for the build-out?

Mostly with $7.5 billion of non-recourse project financing, plus a $1.07 billion parent revolver; it says no new equity is needed for these projects.

Other companies on the tracker

Back to the AI data center tracker. This page is information, not investment advice.

Important: Educational Purposes OnlyThe data, charts, treasury tracking metrics (including mNAV and SPS), and research provided on CryptosEyes.com are for informational and educational purposes only. They do not constitute certified financial, investment, or trading advice. Digital assets like Bitcoin and Ethereum are highly volatile. Always conduct your own research and consult with a registered financial advisor before making investment decisions.