Bitcoin miner · Landlord (leases built data halls)
Hut 8 (HUT) AI data centers
Hut 8 is building two AI data center campuses with turnkey leases: River Bend in Louisiana (245 MW of critical IT) and Beacon Point in Texas (two 352 MW leases with one tenant). It puts total base-term contract value at about $26.6 billion. The first data hall is due in the second quarter of 2027, so nothing is operating yet.
Figures checked on November 18, 2026 against Form 10-Q and Q3 2026 results (November 4, 2026). Every number links to the document it came from.
On this page
Key figures
| Figure | What the company reports | Source |
|---|---|---|
| Contracted capacity | 949 MW (245 + 352 + 352) | Form 10-Q and Q3 2026 resultsas of November 4, 2026 |
| Operating (billing) capacity | None yet (first hall Q2 2027) | Q3 2026 resultsas of November 4, 2026 |
| Pipeline | 3,180 MW under exclusivityGross power, not critical IT load | Q3 2026 resultsas of November 4, 2026 |
| Contract value | About $26.6B | Q3 2026 resultsas of November 4, 2026 |
| Debt | $7.5B non-recourse project financing | Press release filed Sep 28, 2026as of September 28, 2026 |
| Cash | $157M | Form 10-Q, Q3 2026as of September 30, 2026 |
A figure the company has not disclosed shows as n/a. Capacity is critical IT load unless marked as gross power, so compare like with like on the leaderboard.
Tenants and partners
Fluidstack (Anthropic partnership) Named in press reports
River Bend, 245 MW of critical IT on 330 MW of utility capacity; reported as part of a multi-gigawatt partnership with Anthropic
DatacenterDynamics reportNot named (investment-grade tenant) Not named
Beacon Point, two 352 MW leases on 1,000 MW of utility capacity; Phase 2 alone is about $9.8 billion of base-term value
Q3 2026 results
Landlord or GPU owner?
Does not own GPUs for these campuses; the leases are triple-net and take-or-pay. Hut 8 is exiting its small Traditional Cloud business.
How the four models differ in risk and return is explained in landlord, powered land or GPU cloud.
What Hut 8 said on its latest call
Q3 2026 results and call, November 4, 2026. From Results release filed with Form 8-K.
- CEO Asher Genoot said both projects are expected "to be funded entirely at the project level, without requiring equity issuance or recourse debt at the parent".
- The Beacon Point tenant signed a second 352 MW lease, "doubling its contracted capacity at the campus"; expected average annual NOI across Beacon Point is about $1.3 billion.
- Energy capacity under exclusivity rose by 1,300 MW to 3,180 MW, and Hut 8 agreed to buy two energized West Texas sites (up to 230 MW) for up to $180 million.
- Hut 8 bought back $74.7 million of shares in the quarter and $175.3 million more after it, paid for by selling bitcoin.
Two campuses, all leased before they are built
River Bend in St. Francisville, Louisiana is a turnkey data center with 245 MW of critical IT on 330 MW of utility power. Structural steel and foundations are complete across all four data halls and the substation is partly energized; the first hall is due in the second quarter of 2027. The tenant is reported to be Fluidstack, as part of its partnership with Anthropic; the filings do not name it.
Beacon Point in Texas has 1,000 MW of utility capacity under construction for two 352 MW leases with the same, unnamed, investment-grade tenant. Phase 1 is due in the third quarter of 2027 and Phase 2 in the second quarter of 2028. Hut 8 puts the Phase 2 lease at about $9.8 billion of base-term value and about $655 million of average annual NOI, and the campus as a whole at about $19.6 billion and $1.3 billion.
How it is funded
Hut 8 has raised $7.5 billion of fully amortizing, non-recourse, investment-grade project financing for the two campuses, including $3.25 billion of notes for River Bend. In September it added a $1.07 billion revolving credit facility at the parent. Cash was only $157 million on September 30, 2026, but Hut 8 held 16,787 bitcoin (3,090 of them pledged to Bitmain), which it has been selling to fund buybacks.
Recent news
- 2026-09-28Closed a $1.07 billion four-year senior secured revolving credit facility led by J.P. Morgan. (Press release filed with Form 8-K, Sep 28, 2026)
What to watch next
- The first River Bend data hall in the second quarter of 2027, the company's first AI revenue at scale.
- Whether Hut 8 or its tenant names the Beacon Point customer.
- Closing of the two West Texas sites and how much of the 3,180 MW under exclusivity becomes contracted.
Hut 8 AI data center FAQ
Who leases Hut 8's data centers?
River Bend is reported to be leased to Fluidstack as part of its Anthropic partnership. Beacon Point's tenant is described only as investment-grade and has not been named.
When does Hut 8 start earning AI data center rent?
The first data hall is targeted for the second quarter of 2027 at River Bend, then Beacon Point Phase 1 in the third quarter of 2027 and Phase 2 in the second quarter of 2028.
How is Hut 8 paying for the build-out?
Mostly with $7.5 billion of non-recourse project financing, plus a $1.07 billion parent revolver; it says no new equity is needed for these projects.
Other companies on the tracker
- Core Scientific (CORZ)
- IREN
- Cipher Digital (CIFR)
- TeraWulf (WULF)
- Galaxy Digital (GLXY)
- Riot Platforms (RIOT)
- Applied Digital (APLD)
- CleanSpark (CLSK)
- MARA Holdings (MARA)
- Bitdeer (BTDR)
- HIVE Digital Technologies (HIVE)
- Keel Infrastructure (formerly Bitfarms) (KEEL)
- Nebius Group (NBIS)
- CoreWeave (CRWV)
Back to the AI data center tracker. This page is information, not investment advice.